September was busy month in wind power, with dozens of projects RSS Feed

September was busy month in wind power, with dozens of projects

The Colorado Public Utilities Commission approval on Sept. 30 of the 600 MW Rush Creek Wind Project of Xcel Energy’s Public Service Co. of Colorado unit capped off a very busy month of September for the wind power industry.

Here is a rundown of some of the highlights from September, as reported by GenerationHub, for wind power project development:

· Xcel’s Rush Creek Wind Project would be one of Colorado’s largest wind farms, comprised of two generation sites and a 90-mile high-voltage transmission line to tie into Xcel’s electric system. In total, the project would include 300 wind turbines on about 116,000 acres in Elbert, Lincoln, Kit Carson and Cheyenne counties. Construction is expected to begin in 2017 with anticipated commercial operations expected to begin in late 2018.

· NextEra Energy Resources proposes to connect project #AA2-148, a 175 MW (22.75 capacity) wind facility to the American Electric Power transmission system at the in-line switching station proposed to be built as an attachment facility for PJM queue positions W4-004 and W4-008. The new switching station is located between the Madison and Tanners Creek 138 kV substations in Indiana, said a September 2016 study on the project from PJM Interconnection. The location of the proposed wind facility is in Henry County, Indiana. The requested in-service date is Dec. 31, 2017. The study said this will facility will consist of 98 General Electric 1.79 MW wind turbines.

· US Wind Inc. has proposed a 247.8 MW MFO (64.4 MWC) offshore wind facility to be located in the Atlantic Ocean about 14 miles off the coast of Ocean City, Maryland. A September 2016 study on the project from PJM Interconnection said that PJM studied this project, under queue #AB1-056, as a 247.8 MW injection into the Delmarva Power and Light system and evaluated it for compliance with reliability criteria for summer peak conditions in 2019. The planned in-service date, as stated during the kick-off call, is March 1, 2020. PJM issued a similar September 2016 study showing that US Wind has proposed a 251.8 MW MFO (65.4 MWC) wind facility to be located in the Atlantic Ocean about 14 miles off the coast of Ocean City, Maryland. PJM studied this project, under queue #AB1-057, as a 251.8 MW injection into the Delmarva Power and Light system at the Indian River 230-kV Substation and evaluated it for compliance with reliability criteria for summer peak conditions in 2019. The planned in-service date, as stated during the kick-off call, is March 1, 2020.

· Chisholm View Wind Project II on Sept. 29 requested that the Federal Energy Regulatory Commission issue an order that accepts its market-based rate schedule. Applicant owns a wind project with a nameplate rating of 64 MW currently under development and located in Grant and Garfield counties, Oklahoma. The project will be interconnected with the transmission system owned by Oklahoma Gas & Electric within the Southwest Power Pool balancing authority area. Chisholm View expects the project to begin testing in late fall 2016 and to enter commercial operation in late December 2016. It is committed to sell the full output of the project under a 25-year power purchase agreement with Arkansas Electric Cooperative Corp.

· The Federal Energy Regulatory Commission on Sept. 28 approved a July 18 filing by Kelly Creek Wind of a petition for authorization to make market-based sales of energy, capacity, and certain ancillary services under a market-based rate tariff. Kelly Creek, which is indirectly wholly-owned by EDF Renewable Energy (EDF-RE), is developing and will own and operate an about 184 MW (nameplate) wind facility and related generation interconnection facilities to be located in Ford and Kankakee counties, Illinois. The facility was expected to produce test power in late September 2016. It will be interconnected to the transmission system owned by Commonwealth Edison and operated by PJM. All the electric energy and capacity from the facility will be sold into the PJM market.

· Avangrid Renewables representatives, joined by Vermont Gov. Peter Shumlin (D) and local elected officials, broke ground on the 30 MW Deerfield Wind project on Sept. 19. Once operational, Avangrid Renewables signed a 25-year power purchase agreement for the project with Green Mountain Power in 2015. Deerfield, located in Searsburg, Vermont, is expected to become operational by the end of 2017. The project will include 15 Gamesa wind turbines and will be the first utility-scale project on U.S. Forest Service land in the country.

· Invenergy Wind Development has proposed a wind facility located about one mile from the existing 138-kV Baker Substation in Hardy County, West Virginia, said a September 2016 study on the project from PJM. The installed facilities will have a total capability of 121.6 MW with 15.8 MW of this output being recognized by PJM as capacity. The proposed in-service date for this project is Dec. 31, 2018. This study does not imply a Potomac Edison commitment to this in-service date. This project, under PJM queue #AB1-149, will interconnect with the Potomac Edison transmission system through direct injection into the Baker substation 138-kV bus. The facility would consist of 38 General Electric 3.2 MW wind turbines.

· The Minnesota Public Utilities Commission on Sept. 26 went out for comment on applications from Red Pine Wind Project for a Certificate of Need (CON) and Large Wind Energy Conversion System Site Permit for the 200.1 MW Red Pine Wind Project in Lincoln County, Minn. The initial comment period closes Oct. 10, and the reply comment period closes Oct. 17. On Sept. 16, Red Pine Wind Project filed a petition for a Certificate of Need and the application for a Site Permit for an up to 200.1 MW wind project in Lincoln County. The project would entail construction of 58 to 100 wind turbines, associated facilities, four meteorological towers, access roads, and an operations and maintenance building. Red Pine said it is engaged in discussions with multiple potential power offtakers and is evaluating options to proceed with construction of the project in either 2017 or 2018 (commercial operation date of December 2017 or December 2018, respectively). Red Pine is a wholly-owned unit of EDF Renewable Energy. Red Pine has not made a final wind turbine selection, but is currently considering Vestas V100, V117, and V126 turbines.

Read full article at EL&P