PJM Outlines for EPA the Need to Coordinate Outages Resulting From Coal Combustion Rule RSS Feed

PJM Outlines for EPA the Need to Coordinate Outages Resulting From Coal Combustion Rule

PJM, as the independent system operator and planning authority for the grid spanning 13 states and the District of Columbia, last week asked the U.S. Environmental Protection Agency to coordinate the timing of proposed coal plant outages as generators plan upgrades or retirements in response to the EPA’s new Coal Combustion Residual Rule.

In its comments, PJM, noted that 16% of its capacity resources – close to 29,000 MW of PJM’s generation – are impacted by the Coal Combustion Residual (CCR) Rule. “Coordination between PJM and the EPA regarding the sequencing of coal unit outages and retirements as part of the CCR Rule implementation is necessary to ensure the reliability of the bulk electric system,” PJM stated in its comments.

The CCR Rule “establishes technical requirements for CCR landfills and surface impoundments under subtitle D of the Resource Conservation and Recovery Act (RCRA), the nation’s primary law for regulating solid waste,” according to the EPA. The regulations are meant to mitigate risks from coal ash contaminants leaking into groundwater, becoming airborne as dust or escaping during failure of surface impoundments.

PJM does not take a position on the merits of the rule, focusing instead on its generation outage scheduling process and detailing the “fact-specific, case-by-case determination PJM is required to make to ensure the reliability of the bulk electric system when an outage request is submitted for review.”

PJM requests and recommends a formal process in which:

The EPA solicits a recommendation from PJM on the outage scheduling for generators seeking to comply with the new CCR Rule requirements.
PJM would then “endeavor to complete an analysis and tender a recommendation within 60 days as to the sequencing and timing of needed planned outages that would allow for the EPA’s directives to be timely effectuated while ensuring the continued reliability of electric service in the PJM region.”
Ensuring Reliable Operations Year-Round
PJM’s outage coordination request is rooted in specific bulk electric system requirements to reliably fulfill electricity demand, especially during unexpected events.

For example, special attention and flexibility may be required for generator outage requests proposed around summer, when electricity usage is the highest of the year, PJM said.

Read full article at Inside Lines