#Luminant to Close Two Texas Power Plants RSS Feed

Luminant to Close Two Texas Power Plants

RVING, Texas, Oct. 13, 2017 /PRNewswire/ — Luminant, a subsidiary of Vistra Energy (NYSE: VST), today announced that it will close two coal-fueled power plants in Central Texas: its two-unit Sandow Power Plant in Milam County and its two-unit Big Brown Power Plant in Freestone County. In total, approximately 2,300 MW of nameplate power will be taken offline in early 2018.

These two plants are economically challenged in the competitive ERCOT market. Sustained low wholesale power prices, an oversupplied renewable generation market, and low natural gas prices, along with other factors, have contributed to this decision.

Curt Morgan, Vistra Energy’s president and chief executive officer, said, “This announcement is a difficult one to make. It is never easy to announce an action that has a significant impact on our people. Though the long-term economic viability of these plants has been in question for some time, our year-long analysis indicates this announcement is now necessary. These employees have kept both plants reliably powering Texas for decades, and we greatly appreciate their service.”

Sandow Site
Earlier this week, the company and Alcoa entered into a contract termination agreement pursuant to which the parties agreed to an early settlement of a long-standing power and mining agreement. In consideration for the early termination, Alcoa made a one-time payment to Luminant. The settlement follows a decrease in wholesale power prices in ERCOT and the prior curtailment of Alcoa’s smelter operation next to Sandow. The contract has helped shield Sandow from significant exposure to the downturn in the wholesale power market; however, the standalone economics of the Sandow complex no longer support continued investment in the site in this low wholesale power price environment.

Also closing will be Three Oaks Mine, located primarily in Bastrop County, which supports this plant.

Luminant estimates that approximately 450 employees will be impacted by the Sandow plant and Three Oaks mine closure. Eligible and affected employees will be offered severance benefits and outplacement assistance.

As part of the closure process, today Luminant filed a 90-day notice of suspension of operations with ERCOT, which will trigger a 60-day reliability review. If ERCOT determines the Sandow units are not needed for reliability following this 60-day review, Luminant expects to cease plant operations on Jan. 11, 2018.

Luminant will take the necessary steps to responsibly decommission the facility in accordance with all federal and state regulations. In addition, ongoing reclamation work will continue at Three Oaks Mine.

Big Brown Site
Over the last few years, the Big Brown team has made tremendous operational adjustments to remain viable given the challenging market conditions. However, despite these best efforts, the economics of operating Big Brown do not make it a sustainable option for our fleet. The company will explore a sales process for the site during the ERCOT notification period.

Read full article at Markets Insider